Pages

Monday, December 09, 2013

some Pepco power outages in Bloomingdale this week

From: "Mobley, Levonnia (Council)" 

Sent: Thursday, December 5, 2013 9:36 AM
Subject: FW: Update on Pepco work in Bloomingdale 

Bloomingdale Community,

Please see update from Pepco in the following email.

Thanks,

L. Jeannette Mobley
Chief of Staff
Office of Councilmember Kenyan R. McDuffie, Ward 5
Chairman Pro Tempore
Chair, Committee on Government Operations
1350 Pennsylvania Ave. NW, Suite 506
Washington, DC 20004
202-724-8028 (Main)
202-724-8053 (Direct)
JMobley@dccouncil.us

From: crtaylor@pepco.com [mailto:crtaylor@pepco.com]
Sent: Thursday, December 05, 2013 9:09 AM
To: crtaylor@pepco.com
Cc: kmbowden@pepco.com; Mandel, Jon (Council); Mobley, Levonnia (Council); McDuffie, Kenyan (Council); dcooper@pepco.com
Subject: Re: Update on Pepco work in Bloomingdale
           
Good Morning,

Pepco is nearing the completion of the project to convert Feeder 147 from 4 kV - 13 kV, which would increase the capacity to the area. Crews have completed the conduit work and have installed the new cable. The final aspect of this project entails converting customers to the new feeder. In order to complete this conversion, we will need to de-energize customers.
 
We have scheduled this work to occur overnight next week.  Each customer will experience a service interruption over the period of one night.  The outages will occur from 11 p.m. until 6 a.m.  Scheduled outages will occur each night from Monday through Friday night.  Customers requiring a scheduled outage will be notified via a door hanger with the date and times of their service interruption. Please note that customers will only be impacted by outages on one night, not on all five nights. If customers do not receive a door hanger, they should not be impacted by this work. 

 
I also wanted to share with you that these scheduled outages will be cancelled if the overnight weather drops below freezing.  The language included on the notification is as follows:  "Please note that this scheduled work will be cancelled if the weather is below 32 degrees and will be rescheduled when the temperature permits."
                   
We will also be notifying impacted customers with an outbound call.  
   
If you have any questions or concerns, please let us know and we will be glad to follow up. 

   
Thanks,

Chris Taylor
Public Affairs Manager, DC Region
Pepco Headquarters
701 9th St. NW
Washington, DC 20068
Office- 202.872.3357
 

No comments:

Post a Comment