DC Water: 1st St NW between Channing & Michigan Av NW closed all week next week

                
From:Emanuel D. Briggs (Emanuel.Briggs@dcwater.com)
Sent:Thu 1/02/2014 3:41 PM
To:Emanuel D.Briggs
Cc:Emanuel D.Briggs

DC Water Contact:
Emanuel D. Briggs
Manager, Community Outreach
(202) 787-2003
 
January 2, 2014
 
Traffic Advisory
McMillan Construction Brings Traffic Impacts to First Street
Updated Closure Information for Week of January 6
                                                
(Washington, DC) – DC Water is performing construction activities on First Street, NW as part of the McMillan Stormwater Storage Project.
 
During the week of Monday, January 6, First Street between Channing Street and Michigan Avenue will be completely closed to both northbound/southbound traffic. It is advised that North Capitol Street be used as an alternative route for travel on First Street.
 
Important Information:
  • Construction operations for all partial road closures will be from 7:00am to 7:00pm, Monday through Friday; construction operations for all full road closures will be 24 hours, Monday through Saturday.
  • Temporary traffic signs will be set up throughout the area to alert motorists to the upcoming traffic changes.
  • Some traffic delays within the vicinity of the work zones are anticipated.
  • Sidewalk detours will also be implemented.
  • There will be an increase in truck traffic.
  • Noise levels will be closely monitored during construction.
Project Details
DC Water will construct two underground structures to divert stormwater into a temporary holding tank within the McMillan Sand Filtration Plant and existing trunk sewer.  The two diversion structures at North Capitol Street and First Street will work together with the retention basins along Irving Street to delay approximately 4.5 million gallons of stormwater from reaching the Bloomingdale and LeDroit Park neighborhoods during heavy rainfall events. 
 
This is a two-phase project.  The first phase, completed in 2013, included removal of sand from two tanks.  The second phase of the project is currently underway, and includes work on North Capitol Street, First Street and Irving Street.
 
###
 
About DC Water
The District of Columbia Water and Sewer Authority (DC Water), is an industry leading multi-jurisdictional regional utility that provides drinking water, wastewater collection and treatment to 600,000 residential, commercial and governmental customers in the District of Columbia, 17.8 million annual visitors and also collects and treats wastewater for 1.6 million customers in Montgomery and Prince George's counties in Maryland and Fairfax and Loudoun counties in Virginia.
 
DC Water’s service area covers approximately 725 square miles and the company operates the world’s largest advanced wastewater treatment plant with a capacity of 370 million gallons per day and a peak capacity of 1.076 billion gallons per day. 