Pages

Monday, July 25, 2016

DC Water 1st Street Tunnel Forum meeting -- Thursday, 07-28-2016

From: Hadiah Jordan [mailto:Hadiah.Jordan@dcwater.com]
Sent: Monday, July 25, 2016 2:04 PM
Cc: CreativePages, LLC; Ronald Davis <Ronald.Davis@dcwater.com>
Subject: Reminder: First Street Tunnel Forum Meeting

Greetings First Street Tunnel Stakeholders,
Friendly Reminder to join us at the next Tunnel Forum Meeting:
Thursday, July 28, 2016

Please join us on Thursday, July 28, for the 2016 Summer Tunnel Forum Community Meeting.  At this week’s community meeting, the project team will share with you the construction status, schedule for local roadway openings, restoration plans, Small Diameter Water Main Replacement Project update, and more.   
The meeting will be held at:
St. George’s Episcopal Church
160 U Street, NW
Washington, DC  20001
7 pm – 8:30 pm

Updates at Construction Staging Areas (CSAs):

Adams Street and Flagler Place CSA:  Near surface concrete structures are complete.  Utility work including water service connection and storm structure installation with site restoration on Flagler Pl will continue through August.  Shaft internal structures and cover installation with site restoration on Adams St will continue through early September. 
                                                                                
Intersection of First Street and V Street CSA:  Near surface concrete structures are complete on First St and remaining utility work (water and storm structure installation) with surface restoration is scheduled to be complete by mid-August.  V St near surface structures and shaft internal structure/cover installation will continue through early September. 

Pumping Station at Thomas Street and First Street CSA:  Near surface concrete structures are complete.  Shaft cover will be complete by end of July.  Mechanical and electrical installations are complete.  Equipment startup/commissioning, utility installation, and site restoration will continue through August.

If you have any questions or concerns, please call the 24/7 Hotline at 1-844-FST-INFO (1-844-378-4636)Please continue to check our web site for updated project information (http://dcwater.com/workzones/projects/first_street_tunnel/).

Looking forward to meeting you,

Hadiah

Hadiah S. Jordan, Public Outreach Coordinator | DC Clean Rivers Project | DC Water | Hadiah.Jordan@dcwater.com
5000 Overlook Avenue, SW | Washington, DC 20032 | t (202) 787-4717 | f (202) 787-4476
Water is Life! | Web | Facebook | Twitter | YouTube | Flickr | LinkedIn

No comments:

Post a Comment