DC Water NEBT: Florida Avenue NW construction site update (dated 04-23-2020)

From: Andy Galli <news@dcwater.com>
Sent: Thursday, April 23, 2020 4:24 PM
Subject: NEBT: Florida Avenue NW Construction Site Update

Construction Look-Ahead

To reply to this email: dccleanrivers@dcwater.com

Northeast Boundary Tunnel Project
Florida Avenue NW
Construction Site Update

April 23, 2020

Greetings Neighbors.

We would like to let you know of some scheduled and upcoming work as part of the Florida Avenue NW Construction Site. The work will take place on Rhode Island Avenue NW, between 3rd Street NW and Florida Avenue NW. As this upcoming work becomes scheduled, we will inform you of its start date and expected duration.

Median Removal on Rhode Island Avenue
In May 2020, DC Water’s contractor will begin removing portions of the medians on Rhode Island Avenue between 2nd Street NW and 3rd Street NW and between 3rd Street and Florida Avenue NW. It is necessary to remove the median portions to allow for lane shifts and create a work area on Rhode Island Avenue to support of the Florida Avenue Construction Site.

Map 1: Aerial view of the Florida Ave NW Construction Site. Areas in yellow indicate where construction will be conducted. White arrows show how traffic will flow around the site. Blue lines reflect parking restrictions.


Travel and Parking Restrictions
  • Travel lanes in each direction of Rhode Island Avenue between North Capitol Street NW and Florida Avenue will be reduced to two lanes.
  • Parking restrictions will be in place on each side of Rhode Island Avenue between Florida Avenue and North Capitol Street.
  • Southbound traffic on the 1800-block of 3rd Street will be limited to right turns only onto Rhode Island Avenue.
Site Mobilization
Once median removal is complete, DC Water’s contractor will begin the mobilization of a construction work area on Rhode Island Avenue, between 3rd Street and Florida Avenue. This work area mobilization will include setting up a site perimeter, potholing for underground utilities, installing erosion and sediment controls, and installing temporary storm water management measures. Mobilization will create a construction work zone that will result in the temporary closure of the middle eastbound and westbound lanes of Rhode Island Avenue.

At this construction site DC Water’s contractor will install vertical soil-freeze pipes. Ground freezing is a construction method used to stabilize the soil around an excavation area.

Potholing and Underground Utilities
Following construction site mobilization, DC Water’s contractor will begin below ground investigations to assess the locations of underground utilities in Rhode Island Avenue between 3rd Street and Florida Avenue. Work will consist of drilling several holes, approximately 1’ X 1’, into the street, and a vacuum truck will remove the underlying soil to locate any electrical or water lines. Upon completion the soil will be replaced, and the site will be restored. The work will take place in the construction site in the median area of Rhode Island Avenue.

Pre-trenching and Guide Wall Work
Following potholing for underground utilities in Rhode Island Avenue, workers will begin pre-trenching and constructing guide walls for near surface structures. Pre-trenching involves excavating a narrow trench approximately 10 feet deep to ensure that no unknown utilities exist within the area planned for future excavation. Guide wall installation involves excavating an area approximately 4 feet wide and 10 feet deep and installing concrete walls to keep the deep excavation machine in proper position as it digs the 90-feet deep shaft. Pre-trenching and guide wall construction should take approximately 6 weeks to complete.

New Pedestrian Detours
The west crosswalk at Rhode Island Avenue NW and 3rd Street NW will be closed. Please follow pedestrian detour signs.

Project Details
The Northeast Boundary Tunnel is the largest component of the Clean Rivers Project. It begins south of RFK Stadium and will extend north to Rhode Island Avenue, NE and west to 6th Street NW. When finished, the approximately five-mile long tunnel segment will complete the Anacostia River Tunnel, a 13.1-mile-long tunnel that ends at the Blue Plains Advanced Wastewater Treatment Plant. This project will significantly reduce chronic flooding in the areas it serves, as well as reduce the amount of combined sewer overflows into the Anacostia River.

For More Information
To receive email updates about NEBT construction, please send an email to dccleanrivers@dcwater.com

24/7 Northeast Boundary Tunnel Project Hotline: (800) 988-6151
Public Outreach Coordinator: Andy Galli, agalli@dcwater.com
Public Outreach dccleanrivers@dcwater.com
Northeast Boundary Tunnel Project: dcwater.com/NEBT
DC Clean Rivers Project: dcwater.com/clean-rivers-project

twitter.com/dcwater

facebook.com/mydcwater/

dcwater.com

youtube.com/user/MyDCWater


Copyright © 2020 DC Clean Rivers, All rights reserved.
Your contact information is listed on the Northeast Boundary Tunnel Stakeholder Database to receive project updates.

Our mailing address is:
DC Clean Rivers
5000 Overlook Avenue SW
Washington, Dc 20032


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.

Email Marketing Powered by Mailchimp

No comments:

Post a Comment