This newsletter
provides an update of the sequence of construction work at the
First Street NW Construction Site. We know how impactful this work
will be on residents and businesses. Our goal is to help you
anticipate the construction work and its impacts for the remainder
of 2019.
FSPS
Construction Work Sequence
1. Mobilization:
DC Water’s contractor for the Northeast Boundary Tunnel (NEBT) is
preparing to mobilize at the First Street Pumping Station
Construction Site located at the intersection of Thomas Street NW
and First Street NW. Mobilization includes installing erosion and
sediment control elements and security fencing around the perimeter
of the site. Work will begin on or about April 8, 2019.
This construction site will remain in
place for 8 months.
Impacts—
24-Hour Parking Restrictions:
- Parking will be restricted on the south side of the
100-block of Thomas Street NW between First
Street NW and the alley.
Pedestrian Access:
- Pedestrians will be directed to walk on the north
side of the 100-block of Thomas Street NW.
2. Median Removal on
Rhode Island Avenue NW:
The contractor is preparing to remove portions of the two medians
on Rhode Island Avenue NW between North Capitol Street NW and 2nd
Street NW. While the construction was scheduled to begin March 11,
work was delayed as we worked with the District Department of
Transportation and the Urban Forestry Division to further reduce
the number of trees removed from the medians while assuring the
construction site is safe. When NEBT construction is complete, the
medians will be restored and new trees will be planted. Median
removal work will be completed in two phases. Work
will begin for Phase 1 on or about April 9, 2019. Phase 2 will
immediately follow Phase 1.
Phase 1:
The contractor will remove the median on Rhode Island Avenue NW between
2nd Street NW and First Street NW to prepare for
detours and lane shifts. Duration—2.5 weeks.
Impacts—
Travel and Parking Restrictions:
- Traffic on Rhode Island Avenue will be reduced from
three lanes to two lanes and 24-hour parking restrictions will
be in place:
- The eastbound side of Rhode Island Avenue NW between 3rd Street NW and First
Street NW.
- The westbound side of Rhode Island Avenue NW between North Capitol Street NW and
2nd Street NW.
Phase 2:
The contractor will remove the median along Rhode Island Avenue NW between
First Street NW and North Capitol Street. Duration—2.5
weeks.
Impacts—
Travel and Parking Restrictions:
- Traffic on Rhode Island Avenue NW will be reduced
from three lanes to two lanes and 24-hour parking restrictions
will be in place:
- The eastbound side of Rhode Island Avenue NW between 3rd Street NW and First
Street NW.
- The westbound side of Rhode Island Avenue NW between North Capitol Street NW and
2nd Street NW.
3. Jet Grout Plant
Installation:
Jet grouting is a construction method for ground improvement
or soil stabilization. Crews will set up the jet grout plant and install
the required instrumentation to monitor operations. We
will update you when this work is scheduled to begin. Duration—3
weeks.
Impacts—
24-Hour Parking Restrictions:
- Parking will be restricted on the westbound side of
Rhode Island Avenue NW near the intersection of First Street
NW. Parking will also be restricted on First Street NW between
Thomas Street NW and Rhode Island Avenue NW.
4. Jet Grouting:
The contractor will install jet grout columns in the intersection
of First Street NW and Rhode Island Avenue NW. Duration—8
months.
Impacts—
Travel and Parking Restrictions:
- Rhode Island Avenue NW between 2nd Street NW and
North Capitol Street will be reduced to two lanes of traffic
in each direction.
- 24-Hour parking restrictions will be in place
on the eastbound and westbound sides of Rhode Island
Avenue NW between North Capitol
Street and 2nd Street NW.
|