From: Thomas.Lindberg@dcwater.com
To: Thomas.Lindberg@dcwater.com
CC: others
Subject: First Street Tunnel Nighttime Work and Holiday Schedule
Date: Tue, 25 Nov 2014 21:05:19 +0000
NIGHTTIME WORK-Tonight, Tuesday, November 25, 2014.
UPDATE on DC Water’s First Street Tunnel work on First Street NW at the intersection of V Street NW.
PEPCO/ Anchor Construction has been relocating high voltage lines across First Street. The emergency work must continue until midnight tonight , Wednesday, November 25th. There will be two crews with the associated lights and construction noise. The sidewalk will remained closed and flaggers and MPD will be present to direct pedestrians around the work through the east alleyway. The relocation work is being performed more slowly than normal to prevent any local power outages. Work will resume tomorrow morning. The sidewalk will be open for the Holiday weekend. After the holiday, the sidewalk will be restored. We apologize for this disruption.
There will be no First Street Tunnel construction activities at any of the four construction staging areas on Thursday-Thanksgiving Day, Friday, Saturday or Sunday (11/27-11/30).
Please call the 24/7 First Street Tunnel Hotline (844) FST-INFO/ (844) 378-4636 with questions or concerns.
Best Wishes for a healthy and safe holiday weekend,
Tom
Tom Lindberg, DCCR First Street Tunnel - Public Outreach | DC Clean Rivers Project | DC Water | 5000 Overlook Avenue, SW | Washington, DC 20032 | t (202) 787-4738 | f (202) 787-4478 | Email: thomas.lindberg@dcwater.com | FST web page: http://dcwater.com/workzones/projects/first_street_tunnel/
No comments: