IMPORTANT COMMUNITY MEETINGS IN YOUR NEIGHBORHOOD
FIRST STREET TUNNEL PROJECT
DC Water is conducting a series of community meetings for residents in the Bloomingdale and LeDroit Park neighborhoods in support of the First Street Tunnel project (FST).
PURPOSE
The purpose of the meetings is to introduce the FST project contractor and provide information about scope and schedule for the construction phase from February 2014 – March 2016.
Skanska/Jay Dee Joint Venture in association with Parsons Brinkerhoff was awarded the DC Water Clean Rivers Project’s First Street Tunnel design-build contract. Four separate meetings will be held to introduce the FST project contractor and provide general construction schedule information. Each meeting will focus on one of the four construction staging areas (CSAs) in the community.
MEETING SCHEDULE
WHERE: All meetings will be held at:
DC Water Bryant Street Pumping Station (West Gate Entrance)
301 Bryant Street, NW – Auditorium, 3rd Floor
7:00pm – 9:00pm
Photo id required. Must be presented at guard station for entrance.
In the case of inclement weather, meeting(s) will be rescheduled for a later date.
WHEN: Tuesday, January 7
Focus on McMillan cells used for Channing Street Mining Shaft
Tuesday, January 14
Focus on First and V Streets
Thursday, January 23
Focus on Flagler and Adams Streets
Monday, January 27
Focus on First and Thomas Streets
WHO: Representatives from DC Water, DC Clean Rivers Project and the FST Project contractor, Skanska-Jay Dee will make presentations and answer questions regarding the construction phase of the FST Project.
FOR MORE INFORMATION, PLEASE CONTACT:
DC Water Team Leader: Tom Lindberg (202) 787-4738
DC Water 24-hr Emergency: (202) 612-3400
DC Water Office of External Affairs: (202) 787-2200
Email: dccleanrivers@DCwater.com