Sent: Monday, May 23, 2016 12:14 PM
To: Thomas Lindberg
Subject: First Street Tunnel Community Update, May 23, 2016
Greetings First Street Tunnel Stakeholders,
Friendly Reminder to join us at the next Tunnel Forum Meeting
this
Thursday, May 26, 2016
Thursday, May 26, 2016
Please join us on Thursday, May 26, for the 2016 Spring Tunnel Forum
Community Meeting.
As you know, the First Street Tunnel project is winding down. At this
week’s community meeting, the project team will share with you the construction
status, schedule for local roadway openings, landscaping topics, the
repurposing of the painted mural doors at two construction staging areas, and
more.
The meeting will
be held at:
St. George’s Episcopal Church
160 U Street, NWSt. George’s Episcopal Church
Washington, DC 20001
from 7 pm – 8:30 pm
We hope to see you there!
Updates at Construction Staging Areas (CSAs)
Adams Street and Flagler
Place CSA: This week, SKJD will begin cutting down the tops of secant
piles to allow for roadway and sidewalk restoration on Flagler Place. As
you may recall, secant piles were installed at the onset of the project as a
ground support system. Cutting off the tops (from 2 to 5 feet down) of
these interlocking concrete piles is required to make room for restoration of
the street, sidewalks, and tree boxes on Flagler Place.
This work is expected to take two weeks
and will involve the alternate closing of a small portion of the sidewalk on
each side of Flagler Place. Direct abutters will have access to their
homes at all times. The work will require the use of jackhammers.
In addition to the secant pile work, construction activities related to the
near-surface structures, the underground adit, and the drop shaft will
continue.
Intersection of First Street
and V Street CSA: SKJD is working in the drop shaft and at the three
diversion chambers. The dominant activities include concrete delivery and
placement, installing manhole hatches and covers, stripping forms from
completed structures, and backfilling around the new structures. These
activities will continue through June 2016.
Pumping Station at Thomas
Street and First Street CSA: SKJD will soon move the crane to the church parking lot
adjacent to the alleyway. It will remain there for about three
weeks. Moving the crane will allow for the installation of an 8-inch
water line. In addition, work will continue on the pumping station,
including internal mechanics and system testing. Construction in this
area should be completed in June 2016.
If you have any questions or concerns,
please call the 24/7 Hotline at 1-844-FST-INFO (1-844-378-4636). Please continue to
check our web site for updated project information (http://dcwater.com/workzones/projects/first_street_tunnel/).
Sincere Regards,
Tom
Tom Lindberg, DCCR First
Street Tunnel - Public Outreach | DC Clean Rivers Project
DC Water | 5000 Overlook Avenue, SW | Washington, DC 20032 | t (202) 787-4738
f (202) 787-4478 | Email: thomas.lindberg@dcwater.com
FST web page: http://dcwater.com/workzones/projects/first_street_tunnel/
DC Water | 5000 Overlook Avenue, SW | Washington, DC 20032 | t (202) 787-4738
f (202) 787-4478 | Email: thomas.lindberg@dcwater.com
FST web page: http://dcwater.com/workzones/projects/first_street_tunnel/