Friday, July 11, 2014

update on DC Water 1st Street Tunnel Flagler/Adams project

An update on the DC Water 1st Street Tunnel project at Flagler and Adams Street NW:


Date: Fri, 11 Jul 2014 13:02:19 -0400
Subject: Flagler/Adams update
From: bloomingdalecc@gmail.com
To: bloomingdalecc@gmail.com

DC Water's latest is that the Flagler/Adams CSA should start around late July or early August.  (That is delayed from January, then May, then June...)
           
It's still not clear what they are doing about the 30 inch water main on Adams.  In May, they said it needed to be completely relocated around the CSA, and that they were starting the design.  This week, they said that they now decided not to relocate the main, they are replacing part of it where it is, and they are still designing.  We'll see. We also haven't learned the revised truck route, but I think they will run trucks on Second.  Also, Councilmember McDuffie has been no help to us so far (if others disagree, please chime in).

Also, the V Street CSA is up and running.  The Bloomingdale Blog is reporting on a sign posted on First Street NW.

1 comment:

JayG said...

ATTENTION ALL: My dog got loose this afternoon. Wondering if anybody picked up a black and white pit bull. blue collar. name is Dro. CALL ME @ 404-213-5802 if you have any info about this.