From: Vickey Wilcher
Sent: Monday, October 19, 2015 11:39 AM
To: Vickey Wilcher;Thomas Lindberg
Subject: FST Community Update
Sent: Monday, October 19, 2015 11:39 AM
To: Vickey Wilcher;Thomas Lindberg
Subject: FST Community Update
Greetings
First Street Tunnel (FST) Stakeholder,
Please see
below for important project related information:
- Community
Hard Hat Tours this Saturday, October 24th:
Here is a great opportunity for residents and project stakeholders to see
DC Water’s local flood relief construction project up close. You will have
the opportunity to see first-hand the main mining shaft, the tunnel boring
machine (Lucy), visit other construction areas and speak to the senior construction
staff. The purpose of Community Hard Hat Day is to provide the community
an opportunity to learn more about this important environmental project.
For
your convenience, three separate tours will be offered: 9:00 am; 12:00 noon and
2:30 pm. If you would like to participate, please set aside two to two and one
half hours on that day. All tours will begin at the main mining shaft site at
2507 First Street, NW, in the SKJD construction trailer, located at the far end
of the site, along the McMillian Sand Filter silos. Parking is
available at the lot across from the main mining shaft site adjacent to the
Army Corps of Engineers entrance or at the Bryant Street lot, corner of 2nd and
Bryant Street NW.
- Pedestrian
Safety Mirror at V Street: SKJD will place a safety
mirror on the east sidewalk at the First and V CSA-as requested by
residents at the previous Tunnel Forum meeting not later than October 31.
- CSA
Expansion at V Street: SKJD plans to alter perimeter
fencing at the VS-CSA in two locations: keeping the west alley closed for
the duration of the project both day and night and enclosing an additional
15’ on the south side of First Street. This will mean the loss of 4-6
parking spaces. It was determined that these two changes were
necessary to safely accommodate the surface equipment required, including
crane operations. Those residents adversely impacted by these changes can
apply for APA parking tags and use the shuttle service. This change will
take place not later than October 31.
- Instrumentation
Repair along First Street: SKJD sub-contractor,
Connolly, has posted temporary “No Parking” signs on the west
side of the 2100 block to upgrade and repair instrumentation equipment
along First Street. The work will continue in the vicinity of the W St
intersection south towards V St. In each area, the work will take about
two days; once the work is done, the No Parking signs will be removed.
This task should be completed by on or about October 31. If
residents have trouble parking on First Street, please apply for an APA
tag to use the off street parking lots and the 24/7 shuttle provided by
the project.
- Lane
Closure-First Street at Thomas Street-SKJD will
be installing a force main (sewer pipe) across First Street in two phases.
One lane of traffic will always be open. Flaggers will be on site to
assist. Lane closures are anticipated to start around the end of November,
and continue for approximately one month.
6. Flagler Parking
Restrictions: Flagler Place-SKJD will be placing temporary No Parking signs
on west side of Flagler Place from W Street to the CSA. As you may
recall, no parking signs are already posted on the east side of the street. The
additional “No Parking” zones are required to accommodate large concrete pours.
We expect this to take place over 4-5 non-consecutive days, with the first pour
taking place on or about Thursday, October 22. SKJD will provide more details
as the work approaches. And 7AM to 7PM parking on the west side of Flagler
Place from W Street to the CSA will be restored after the placements are
complete.
7. FEMS
Mural Project: The second set of completed doors will be ready for SKJD
to install in advance of the Tunnel Tours event.
8. Lucy’s
progress: Lucy, the FST Tunnel Boring Machine is proceeding down First
Street at a pace of approximately 50 feet a day, and has crossed Bryant Street,
where she will stop for some scheduled maintenance.
9. FST Forum Reminder: The next Tunnel will be on
Thursday, October 22, 2015 at 7:00 P.M. at St. George’s Episcopal Church at 160
U Street, NW.
As always,
please don’t forget to avail yourselves of the 24 Hour FST
Hotline—1-844-FST-INFO [1-844-378-4636]—if you have any questions or
concerns about the project. Equally important, if you have not checked the FST
website in a while, please visit at: https://www.dcwater.com/workzones/projects/first_street_tunnel/
We appreciate
your participation and support in this very important project
Sincere
Regards,
The FST
Outreach Team
Tom Lindberg, DCCR
First Street Tunnel - Public Outreach | DC
Clean Rivers Project | DC Water | 5000 Overlook Avenue, SW
| Washington, DC 20032 | t (202) 787-4738 | f (202)
787-4478 | Email: thomas.lindberg@dcwater.com | FST web
page: http://dcwater.com/workzones/projects/first_street_tunnel/
Vickey M. Wilcher | Public Outreach Officer | DC Clean Rivers Project |
DC Water
No comments:
Post a Comment